This project involved the refurbishment of an existing McDonalds Restaurant to a new livery and design – Restaurant of the Future. In order to keep disruption to a minimum, the restaurant was closed down and a programme of 24/7 continuous working carried out over six weeks. The works included:

  • Removal of existing block paviours and ground works to facilitate new side by side Drive Thru

  • Casting slabs for new small booth extension.

  • Casting slab at new reduced level for freezer extension

  • Demolition of old external store and break wall through for freezer extension

  • Construction of new Metsec wall to booth extension

  • Installation of new freezer and food store

  • Fit new glazed windows to new booths and shop fronts

  • Extension to existing Mansard roof

  • Installation of external brick slips

  • Fit new internal glazed screens

  • Installation of new lighting

  • Refurbishment of existing toilets

  • Removal of section of wall in corridor to create new cleaners cupboard

  • Alterations to the drainage in kitchen

  • Electrical/Mechanical/Data cabling works as required when forming the new layout

  • Construction of new McCafe and Oat walls

  • Fitting a new suspended ceiling in kitchen and Crew Room

  • New wall and floor tiling

  • New vinyl floor to Crew Room

  • Fitting new wall boards to Crew Room

  • Decoration

  • New graphics to the restaurant area

  • Installation of new kitchen equipment

  • Replacement of restaurant fixtures and fittings

  • Installation of a new counter and digital menu boards

  • Removal of existing & installation of new internal signs.

  • Installation of CCTV and fire alarm

  • Installation of new external signage

  • Car park works